table of contents

Third Quarter 2006         

 

High construction costs hitting local government projects hard ?

If you’ve ever thrown a party and nobody showed up, you know how Port Orange City Manager Ken Parker felt when city officials went out for bids on a major construction
project and received no responses. Not one.

“We had planned to make repairs and improvements to the city’s gymnasium and create space for preschool and PAL (Police Athletic League) programs,” said Parker. “We expected bids to come in at $1.3 - $1.4 million. When bids were due, none were received.”

Parker’s team contacted potential bidders to see why nobody wanted the business and
learned they feared committing to a fixed price when costs are so uncertain. One potential bidder decided not to bid when his own cost calculations for the project approached $5 million. A construction manager was asked to run the numbers and found the cost of the project had soared to $4.2 - $4.5 million between the time it was it was planned and the time when bids were solicited.


10th Street widening secures new high school;
this county project was millions over original estimates

The escalating cost of construction, an active construction market and pricing uncertainties are straining local governments across Volusia County. Dozens of planned and much-needed projects are being delayed due to budget shortfalls at a time when the county’s growing population is straining existing infrastructure – from roads to schools.

“We are moving forward with the most essential elements of the project – roofing and
siding work at the gymnasium, but the additional space for pre-school and PAL programs is under review,” said Parker.

The impact of rising construction costs was foreshadowed in Port Orange when a 2005
proposed bond issue of $14 million to build a new police station, two fire stations and other projects came up short, and the city allocated $17 million for the work, only to have estimated pricing come in at $21 million. The city had planned public meeting spaces in the fire stations hoping to fill a need for public meeting space and returning fire stations to a time when they are a center of community life. “We are now in discussions with architects over just what $17 million actually will buy,” said Parker.

Escalating costs also have taken a toll on essential road construction. South Williamson
Boulevard in Port Orange has become more heavily traveled and was a priority in Volusia County’s five-year road program. Construction was expected to occur in 2009. Now, the project could be delayed until 2015.

DeLand also has had a similar experience. “Inflationary costs have had a significant impact on our construction projects,” said DeLand City Manager Mike Abels. For example, the city’s street resurfacing and sidewalk construction program required an additional appropriation of $200,000.

DeLand’s new city hall, scheduled for occupancy next month, with a grand opening
slated for March, will have cost $10 million, or nearly $2 million more than budgeted when the project went to bid in 2003.

The inflationary costs for projects including construction of DeLand’s new city hall, a new fire station and renovation of the central fire station approached 25 percent from
the time costs were estimated to the time bids were received and contracts were secured. This represents $2.5 million in increased costs between 2003 - 2005.

The challenges are similar at the Volusia County School District, which is striving to
build and renovate schools to accommodate its growing student population. There are 75 public schools in Volusia County that serve a student population of 65,400. There are three elementary schools under construction or about to begin construction, as well as one middle school, one high school and a combined middle/high replacement school.

Jack Dunlop, Director of New Construction and Inspections for Volusia County Schools,
said that while costs always are relative to supply and demand, the past five years have been particularly busy worldwide, putting pressure on the supply of materials and driving prices skyward.

The building of a new school typically is a cooperative venture. Volusia County Schools
builds the school plant, while Volusia County Government handles road construction. “The county people are incredibly cooperative and go out of their way to do what has to be done in road construction to help us keep up with our school construction program,” said Dunlop. Just the same, when a road project along Clyde Morris Boulevard had to be postponed by the county, school district officials had to authorize
and fund the construction of turn lanes and other road work to ensure Hinson Middle
School in Daytona Beach could commence operations.

The school system’s highest profile and most expensive project is the planned new high school in Orange City, currently called high school DDD. When bids were solicited for DDD, only one bid was submitted. A second request for proposals was issued which yielded only two bids. The school will be a major addition to the lineup of high schools and will serve 2,500 students. Its $95 million price tag includes $5 million for site work and $1 million for a mechanical plant that will serve DDD and middle school DD. By comparison, the new high school in New Smyrna Beach serves 2,100 students and was constructed at a cost of about $40 million.

High school DDD also is larger than the new Mainland High School, which was built at
a cost of about $49 million including $1.5 million for a temporary campus so classes could continue through the construction, and $2.5 million for the Vince Carter Athletic Center, funded by Carter, a National Basketball Association star and Mainland alumnus.

Pat Drago, Executive Director of Facilities Services for Volusia County Schools, said the cost of building elementary schools three years ago was about $11 million each, compared to $17 million today. All of this illustrates the challenges of keeping up with school construction in an environment of high prices.

Of critical importance is the impact of escalating costs on Volusia County’s road construction program. Cost increases are striking. Materials costs are up significantly.

The cost of pouring concrete sidewalks is up 45 percent; curbing is up 60 percent; and liquid asphalt is up a stunning 120 percent. Translating some of these statistics into dollars, the cost of resurfacing a mile of road is up from $40,114 to $93,622. This represents millions of dollars in increased expenditures.

“We had been accustomed to yearly increases in construction costs of 3 - 5 percent
and budgeted accordingly,” said Jerry Brinton, County Engineer. “The huge spike in costs for land for right-of-way use and construction have had a dramatic effect on our five-year road program, which is more like a 10-year program as a result.” He added that priorities have to be reviewed frequently.

The road building funding shortage is so critical and so important to the community that County Manager Jim Dinneen recently convened a meeting of county and city officials.

And when Brinton was interviewed for this article, he was on his way to a similar summit being hosted by the Florida Department of Transportation for city and county officials in the region.

In spite of the difficult market conditions, Volusia County remains active in road
construction because the Volusia County Council previously bonded gas tax revenues,
taking advantage of low interest rates and advancing $65 million available to fund projects.

These funds will have been spent by the end of next year, according to Brinton.
It’s a challenging time for Brinton, his counterparts in the cities and construction
managers. While construction costs are well above estimates, there may be a bit of relief on the horizon. “We have seen signs the market is becoming more competitive,” said Volusia County Schools’ Drago. “While the cost of materials has not come down, the cost of labor has.”

Abels and Parker concur and said they have seen some stabilization of construction prices recently. According to Brinton, another factor causing increased competition among contractors is the fact that the Florida Department of Transportation has fewer
projects going out to bid at this time, resulting in the availability of more bidders for county and city work. Bids for the Clyde Morris Boulevard project that was to have served Hinson Middle School and had been delayed recently was put out to bid and attracted several bids, signaling at least the hint of a return to a more balanced market.


Department of Economic Development
700 Catalina Drive, Suite 200, Daytona Beach, FL 32114
Telephone:
386-248-8048   FAX: 386 238-4761   Toll Free: 800-554-3801

Richard Michael
Director

doed@volusia.org